The Project aims at enhanced sustainable management of the Nairobi Rivers that support natural ecosystems regeneration, socio-economic activities, and improved livelihoods. The rivers in the Nairobi Basin include; the Nairobi River, Ngong river, Mathare river, Kiu river, Riara river, and Gatharaini river.

African Development Bank (AfDB) finances the project for an implementation period of 4 years from 2019-2023.

The project’s goal is to contribute to sustainable development through improved health and environmental management.

Specific objectives of the programme include:
1. To increase sewerage coverage in Nairobi City from the current 48% to 55% by 2023 by serving over 400,000 residents.

2. Reducing pollution levels of Nairobi River by collecting and treating 80,000m3/d of waste water.

3. Enhance sustainability of sewerage operations through increased revenue collection.

Lot 2 - Construction of Kahawa West, Githurai 44 & 45 and Kahawa Sukari reticulation Sewers

Scope of Works. Construction of:150 km of reticulation sewers.
. Construction of 4000 nr House hold connections
. 2nr Faecal Sludge Disposal Points.

Lot 3 - Construction of Mwiki & Clay works reticulation Sewers

Scope of Works. Construction of 140 km of reticulation sewers.
. Construction of 4000 nr House hold connections
. 2nr Faecal Sludge Disposal Points.

Lot 4 - Construction of East and West of Nairobi Reticulation sewers

Scope of Works

. Construction of 130km of reticulation sewers in various areas of East and West of Nairobi.

. Construction of 3000 nr House hold connections
. Securing of the Karen Waste Water treatment plant and Site ancillary works.

Lot 5 -Construction Works for Extension of Water and Sewerage Intervention for Informal Settlements

Scope of Works

. Construction of 25 No. Ablution Blocks in the selected areas

. Construction of 10 No. Pilot Fresh-life toilets in Mukuru
. Construction of 35 KM of Simplified sewers to achieve at least 700 No. last mile household connections